Ballyegny More
Ballyegny More is a townland in the civil parish of Clonagh, barony of Connello Lower, Co. Limerick. Its name in Irish is Baile Éignigh Mór.
Parcel 1645208
- Area
- 251,818 m² (25.18 ha, 62.23 acres)
- Buildings
- 4 buildings touch it. Their footprint covers 541 m².
- Zoning
- No zone of a development plan covers it in the national zoning. Outside zoned towns and villages, the county development plan's rural policies apply.
- Townland
- Ballyegny More
Planning applications on this parcel
19 Dec 2025Refused
six (6) wind turbines with a tip height of 158m, a rotor diameter of 136m and all associated foundations and hardstanding areas. A 38kV on-site substation compound containing a substation building, associated electrical equipment and transformers with separate client side and ESB entrances. The building will contain a control room, switchgear room, ESB room and store room, underground electrical and communications cabling between the wind turbines and on-site substation. Grid Connection Option A: 2.54km-long 38kV underground cable connection from the on-site substation to the existing Carrons substation to the west of the site. Grid Connection Option B: Loop into the existing 38kV onsite overhead line via the proposed 38kV substation. A new temporary site entrance off the L1219 local road to the west of the permanent site entrance for the construction phase only. Upgrade of an existing farm entrance and access track off the L1219 local road in the northwest of the site to serve as a permanent site entrance for the wind farm when operational. Approximately 3.4km of new site access tracks with associated turning areas and drainage. This includes approximately 490m of temporary access tracks which will be reinstated following construction. Upgrade of approximately 470m of existing site access tracks. A 9m-long clear span bridge crossing of the Ahacronane River by an internal site access track to the northwest of turbine T1 and an associated 1.5m x 1.0m relief culvert. A permanent meteorological mast with a height of 90m, a foundation and hardstand. Two (2) material storage areas with a total capacity of approximately 39,300m3. A temporary construction compound with an area of approximately 1,375m2. All associated site development works, including drainage, diversion or undergrounding of low voltage powerlines, landscaping and revegetation. This planning application is accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) which have been prepared in respect of the construction, operation and decommissioning of the proposed development, and works to facilitate turbine delivery from the port of Foynes to the wind farm site entrance via L6188, N69, L1222, L1220 and L1219. The Applicant is seeking a 10-year planning permission and 35-year operational life, initiating from the date of full commissioning of the entire wind farm. This development is covered by the provisions of the Renewable Energy Directive III (Di
Permission · Limerick County Council, 2561367
2 Oct 2025N/a
six (6) wind turbines with a tip height of 158m, a rotor diameter of 136m and all associated foundations and hardstanding areas. A 38kV on-site substation compound containing a substation building, associated electrical equipment and transformers with separate client side and ESB entrances. The building will contain a control room, switchgear room, ESB room and store room, underground electrical and communications cabling between the wind turbines and on-site substation. Grid Connection Option A: 2.54km-long 38kV underground cable connection from the on-site substation to the existing Carrons substation to the west of the site. Grid Connection Option B: Loop into the existing 38kV onsite overhead line via the proposed 38kV substation. A new temporary site entrance off the L1219 local road to the west of the permanent site entrance for the construction phase only. Upgrade of an existing farm entrance and access track off the L1219 local road in the northwest of the site to serve as a permanent site entrance for the wind farm when operational. Approximately 3.4km of new site access tracks with associated turning areas and drainage. This includes approximately 490m of temporary access tracks which will be reinstated following construction. Upgrade of approximately 470m of existing site access tracks. A 9m-long clear span bridge crossing of the Ahacronane River by an internal site access track to the northwest of turbine T1 and an associated 1.5m x 1.0m relief culvert. A permanent meteorological mast with a height of 90m, a foundation and hardstand. Two (2) material storage areas with a total capacity of approximately 39,300m3. A temporary construction compound with an area of approximately 1,375m2. All associated site development works, including drainage, diversion or undergrounding of low voltage powerlines, landscaping and revegetation. This planning application is accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) which have been prepared in respect of the construction, operation and decommissioning of the proposed development, and works to facilitate turbine delivery from the port of Foynes to the wind farm site entrance via L6188, N69, L1222, L1220 and L1219. The Applicant is seeking a 10-year planning permission and 35-year operational life, initiating from the date of full commissioning of the entire wind farm. This development is covered by the provisions of the Renewable Energy Directive III (Directiv
Permission · Limerick County Council, 2561003
Source: National Planning Applications, Department of Housing, Local Government and Heritage, CC BY 4.0. Applicants are not shown.
Designated sites
No designated site (Special Area of Conservation, Special Protection Area, Natural Heritage Area or proposed one) touches this parcel.
Recorded monuments around it
This parcel is in the zone of notification of 2 recorded monuments.
- LI028-038 Ringfort - rath
Description
In undulating pasture, atop gentle rise. Roughly circular area (33m N-S; 30m E-W) defined by scarped edge (H 0.55m; Wth 3.2m), with external fosse (D 0.1m; Wth 1.2m) evident NNE->ENE and W->NNW but truncated by dry-stone field boundary NNW->NNE. Counterscarp bank (int. H 0.1m; ext. H 0.3m) evident NNE->ENE. Interior, under pasture, dips gently down towards centre. Ringfort (LI028-039---) c. 40m to NE. Compiled by: Denis Power Date of upload: 26 August 2011 See attached ASI aerial photographs ASIAP – taken on 04/03/2006.
- LI028-039 Ringfort - rath
Description
In pasture, on gentle E-facing slope. Circular area (22.5m N-S; 22.5m E-W) defined by scarped edge (H 0.6m; Wth 3.9m) NNE->SW, and enclosed by curving field boundary incorporating enclosing bank SW->NNE. Field boundary (int. H 1.5m; ext. H 0.9m) is stepped internally, suggesting lower inner part may be enclosing bank with higher section added to form field boundary. Interior grass-covered and level. Ringfort (LI028-038---) c. 40m to SW. Compiled by: Denis Power Date of upload: 26 August 2011
Architectural heritage
No building of the National Inventory of Architectural Heritage stands on this parcel.
Designated sites: National Parks and Wildlife Service. Recorded monuments: Sites and Monuments Record, National Monuments Service. Buildings: National Inventory of Architectural Heritage. Department of Housing, Local Government and Heritage, CC BY 4.0. Works at or in relation to a recorded monument need two months' written notice to the National Monuments Service (National Monuments (Amendment) Act 1994, section 12).
Ground and risks
- Radon
- At the centre of this parcel, about 1 in 10 homes in this area is likely to have high radon levels. Testing a home
- Landslides
- The 1:50,000 map rates the landslide susceptibility here as low.
- Terrain model
- No LiDAR survey of the Office of Public Works covers the centre of this parcel.
- Flooding
- The Office of Public Works publishes its flood maps on floodinfo.ie.
Radon Risk Map of Ireland, Environmental Protection Agency, and Landslide Susceptibility Classification, Geological Survey Ireland, both under CC BY 4.0. LiDAR: contains Irish Public Sector Data (Geological Survey Ireland & the Office of Public Works) licensed under a Creative Commons Attribution 4.0 International (CC BY 4.0) licence.
Download this parcel as DXF, in Irish Transverse Mercator metres, with its neighbours and buildings, for a drawing program. GeoJSON, in WGS 84, suits a map, and KML opens in Google Earth.
Registered freehold land, Tailte Éireann, CC BY 4.0. A parcel is the land of a title, not an address. The owner's name is in the Land Registry of Tailte Éireann: a copy of the folio can be ordered on landdirect.ie, for a fee.
- Area
- 96.7 ha
- 239 acres
- Land parcels
- 7
- registered freehold, median 189,907 m² (18.99 ha, 46.93 acres)
- Zoning
- —
- not in a zoned settlement
- Planning
- 2
- applications since 2010
Land parcels
Registered freehold land, Tailte Éireann
7 registered freehold parcels lie mostly in Ballyegny More, from 1,223 m² to 283,131 m² (28.31 ha, 69.96 acres). The dashed line is the townland's boundary. 13 neighbouring parcels touch it.
Download the townland as DXF, in Irish Transverse Mercator metres, with its boundary, parcels and buildings, or as GeoJSON or KML.
Zoning
Development plans, national zoning
No zone of a development plan covers Ballyegny More in the national zoning. Outside zoned towns and villages, the county development plan's rural policies apply to each application.
Source: Tailte Éireann and the Department of Housing (MyPlan), national zoning, CC BY 4.0.
Planning applications
Sites that touch the townland, newest first
19 Dec 2025Refused
six (6) wind turbines with a tip height of 158m, a rotor diameter of 136m and all associated foundations and hardstanding areas. A 38kV on-site substation compound containing a substation building, associated electrical equipment and transformers with separate client side and ESB entrances. The building will contain a control room, switchgear room, ESB room and store room, underground electrical and communications cabling between the wind turbines and on-site substation. Grid Connection Option A: 2.54km-long 38kV underground cable connection from the on-site substation to the existing Carrons substation to the west of the site. Grid Connection Option B: Loop into the existing 38kV onsite overhead line via the proposed 38kV substation. A new temporary site entrance off the L1219 local road to the west of the permanent site entrance for the construction phase only. Upgrade of an existing farm entrance and access track off the L1219 local road in the northwest of the site to serve as a permanent site entrance for the wind farm when operational. Approximately 3.4km of new site access tracks with associated turning areas and drainage. This includes approximately 490m of temporary access tracks which will be reinstated following construction. Upgrade of approximately 470m of existing site access tracks. A 9m-long clear span bridge crossing of the Ahacronane River by an internal site access track to the northwest of turbine T1 and an associated 1.5m x 1.0m relief culvert. A permanent meteorological mast with a height of 90m, a foundation and hardstand. Two (2) material storage areas with a total capacity of approximately 39,300m3. A temporary construction compound with an area of approximately 1,375m2. All associated site development works, including drainage, diversion or undergrounding of low voltage powerlines, landscaping and revegetation. This planning application is accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) which have been prepared in respect of the construction, operation and decommissioning of the proposed development, and works to facilitate turbine delivery from the port of Foynes to the wind farm site entrance via L6188, N69, L1222, L1220 and L1219. The Applicant is seeking a 10-year planning permission and 35-year operational life, initiating from the date of full commissioning of the entire wind farm. This development is covered by the provisions of the Renewable Energy Directive III (Di
Permission · Limerick County Council, 2561367
2 Oct 2025N/a
six (6) wind turbines with a tip height of 158m, a rotor diameter of 136m and all associated foundations and hardstanding areas. A 38kV on-site substation compound containing a substation building, associated electrical equipment and transformers with separate client side and ESB entrances. The building will contain a control room, switchgear room, ESB room and store room, underground electrical and communications cabling between the wind turbines and on-site substation. Grid Connection Option A: 2.54km-long 38kV underground cable connection from the on-site substation to the existing Carrons substation to the west of the site. Grid Connection Option B: Loop into the existing 38kV onsite overhead line via the proposed 38kV substation. A new temporary site entrance off the L1219 local road to the west of the permanent site entrance for the construction phase only. Upgrade of an existing farm entrance and access track off the L1219 local road in the northwest of the site to serve as a permanent site entrance for the wind farm when operational. Approximately 3.4km of new site access tracks with associated turning areas and drainage. This includes approximately 490m of temporary access tracks which will be reinstated following construction. Upgrade of approximately 470m of existing site access tracks. A 9m-long clear span bridge crossing of the Ahacronane River by an internal site access track to the northwest of turbine T1 and an associated 1.5m x 1.0m relief culvert. A permanent meteorological mast with a height of 90m, a foundation and hardstand. Two (2) material storage areas with a total capacity of approximately 39,300m3. A temporary construction compound with an area of approximately 1,375m2. All associated site development works, including drainage, diversion or undergrounding of low voltage powerlines, landscaping and revegetation. This planning application is accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) which have been prepared in respect of the construction, operation and decommissioning of the proposed development, and works to facilitate turbine delivery from the port of Foynes to the wind farm site entrance via L6188, N69, L1222, L1220 and L1219. The Applicant is seeking a 10-year planning permission and 35-year operational life, initiating from the date of full commissioning of the entire wind farm. This development is covered by the provisions of the Renewable Energy Directive III (Directiv
Permission · Limerick County Council, 2561003
Source: National Planning Applications, Department of Housing, Local Government and Heritage, CC BY 4.0. Applicants are not shown.
Nature and heritage
Designated sites and recorded monuments
Designated sites
No designated site (Special Area of Conservation, Special Protection Area, Natural Heritage Area or proposed one) touches the townland of Ballyegny More.
Recorded monuments
- LI028-031 Ringfort - rath
Description
In pasture, on N-facing slope and immediately N of avenue to Ballyegny House. Circular area (30.5m N-S; 31.5m E-W) enclosed by earthen bank (int. H 0.4m; ext. H 1.5m), with external fosse (Wth 3.75m) SSW->SSE, and with counterscarp bank (int. H 0.45m; ext. H 0.65m) NNE->SSE. Bank increases in external height (max. H 2.35m) on N side to compensate for slope of ground; internal height is low throughout. Fosse is covered by dense overgrowth SSW->NNW. Interior, which slopes gently down to N, and bank are covered by mature deciduous trees. Field boundary abuts edge of fosse at NNE and a low earthen bank (Wth c. 1.5m; H 0.2m) crosses fosse at SE. Compiled by: Denis Power Date of upload: 26 August 2011
- LI028-035 Ringfort - rath
Description
In pasture, on SW-facing slope; on E side of avenue to Ballyegny House. Circular area (diam. c. 45m) enclosed by earthen bank (int. H 0.5m; ext. H 1.05m), with external fosse (Wth 2.5m) SW->E and counterscarp bank (int. H 0.35m; ext. H 0.4m) SW->N. Interior is covered by dense overgrowth of briars and thorn. Field boundary, depicted on 1923 OS 6-inch map abutting bank at ESE, has been removed. Compiled by: Denis Power Date of upload: 26 August 2011
- LI028-038 Ringfort - rath
Description
In undulating pasture, atop gentle rise. Roughly circular area (33m N-S; 30m E-W) defined by scarped edge (H 0.55m; Wth 3.2m), with external fosse (D 0.1m; Wth 1.2m) evident NNE->ENE and W->NNW but truncated by dry-stone field boundary NNW->NNE. Counterscarp bank (int. H 0.1m; ext. H 0.3m) evident NNE->ENE. Interior, under pasture, dips gently down towards centre. Ringfort (LI028-039---) c. 40m to NE. Compiled by: Denis Power Date of upload: 26 August 2011 See attached ASI aerial photographs ASIAP – taken on 04/03/2006.
- LI028-039 Ringfort - rath
Description
In pasture, on gentle E-facing slope. Circular area (22.5m N-S; 22.5m E-W) defined by scarped edge (H 0.6m; Wth 3.9m) NNE->SW, and enclosed by curving field boundary incorporating enclosing bank SW->NNE. Field boundary (int. H 1.5m; ext. H 0.9m) is stepped internally, suggesting lower inner part may be enclosing bank with higher section added to form field boundary. Interior grass-covered and level. Ringfort (LI028-038---) c. 40m to SW. Compiled by: Denis Power Date of upload: 26 August 2011
- LI028-043 Ringfort - rath
Description
In pasture, on E-facing slope. Roughly circular area (34m N-S; 32m E-W) enclosed by two concentric earthen banks with an intervening fosse. Inner bank evident NNE->NNW, highest along its W half (int. H 0.7m; ext. H 2.75m), but replaced by scarp NNW->NNE; at SSE is break in bank with causeway (Wth 3.4m) across fosse. Slight internal berm (max. Wth 5m; H 0.5m) evident at base of bank SW->NW, possibly due to slumping of bank material. Outer bank of earth-and-stone has an average external height of c. 0.85m but is highest WSW->NNW (int. H 2.2m; ext. H 1.1m), but has been levelled NNW->NNE. Fosse (Wth 3.25m base) covered by dense overgrowth around much of its perimeter. Level interior under pasture. Linear scarp (H 0.95m; long axis N-S) adjacent to outer bank at SW may be associated with removed field boundary. Compiled by: Denis Power Date of upload: 26 August 2011 See attached ASI aerial photographs ASIAP – taken on 04/03/2006.
Architectural heritage
- Ballyegny House, house, 1860–1880 · Regional interest
Description
Detached L-plan three-bay two-storey house, built c. 1870. Pitched slate roof having rendered chimneystacks, overhanging eaves with red brick eaves supports and cast-iron rainwater goods. Roughcast rendered walls having cut stone plinth course to south elevation. Square-headed openings throughout with cut limestone sills. Two-over-two pane and one-over-one pane timber sliding sash windows. Cast-iron sill guard to ground floor window, north elevation. Round-headed opening to west (rear) elevation having tooled limestone sill and timber margin sash stained glass window. Timber framed window to ground floor, west elevation. Segmental-headed opening to east (front) elevation with double-leaf timber panelled door, spoked fanlight and sidelights. Rendered step to entrance. Square-headed opening to rear having timber battened door. Limestone step to entrance. Entrance to south-west comprising pair of square-profile rock-faced limestone piers, joined by sweep walls, flanking double-leaf cast-iron gate.
Designated sites: National Parks and Wildlife Service. Recorded monuments: Sites and Monuments Record, National Monuments Service. Buildings: National Inventory of Architectural Heritage. Department of Housing, Local Government and Heritage, CC BY 4.0. Works at or in relation to a recorded monument need two months' written notice to the National Monuments Service (National Monuments (Amendment) Act 1994, section 12).
Ground and risks
Radon, landslides, flooding
- Radon
- At the centre of the townland of Ballyegny More, about 1 in 10 homes in this area is likely to have high radon levels. Testing a home
- Landslides
- The 1:50,000 map rates the landslide susceptibility here as moderately low, low, partly inferred.
- Terrain model
- No LiDAR survey of the Office of Public Works covers the centre of the townland of Ballyegny More.
- Flooding
- The Office of Public Works publishes its flood maps on floodinfo.ie.
Radon Risk Map of Ireland, Environmental Protection Agency, and Landslide Susceptibility Classification, Geological Survey Ireland, both under CC BY 4.0. LiDAR: contains Irish Public Sector Data (Geological Survey Ireland & the Office of Public Works) licensed under a Creative Commons Attribution 4.0 International (CC BY 4.0) licence.
Homes sold
Property Price Register
No address of the register names Ballyegny More with five sales or more. The sales of the area are on the page of Co. Limerick.
The townland
- Name
- Ballyegny More · Baile Éignigh Mór
- Area
- 966,988 m² (96.7 ha, 238.95 acres)
- Civil parish
- Clonagh, and its townlands
- Barony
- Connello Lower
- Electoral division
- Dunmoylan East, the unit of the census
- Census 2022
- 523 people lived in 180 households in the Dunmoylan East electoral division. 90% of households owned their home. 27% of homes were built since 2001. 6% of dwellings stood vacant on census night, and 2% were holiday homes.
- Neighbouring townlands
- Ballinvulla, Ballyegny Beg, Ballyneety, Ballynisky, Coolcappagh, Dromturk, Graigoor, Rathgoonan
- Placenames
- Ballyegny More on logainm.ie, the Placenames Database of Ireland
Townlands, civil parishes, baronies and electoral divisions, National Statutory Boundaries, Tailte Éireann, CC BY 4.0. Census 2022, Small Area Population Statistics by electoral division, Central Statistics Office, CC BY 4.0. A townland is the smallest land division of Ireland, and the unit of a rural address. Old registers such as the 1901 and 1911 censuses file it under its civil parish and barony.