Land parcel 5465015
Registered freehold, where the statutory boundaries draw no townland, as in the centres of Dublin, Cork and Galway
Parcel 5465015
- Area
- 526 m²
- Buildings
- 1 building touches it. Its footprint covers 92 m².
- Zoning
- R2 Z1: Sustainable Residential Neighbourhoods (Development Plan 2022-2028 (Variation No. 11)) The objective
- Townland
- —
Planning applications on this parcel
2 Jun 2026Additional information
PROTECTED STRUCTURE: Rectone Developments Ltd intend to apply for PERMISSION for a residential development comprising 30 no. units, on a site of c. 0.476 ha., on lands at Balnagowan House, St. Mobhi Boithirin, Glasnevin, Dublin 9 (the western part of the site fronts The Haven). Balnagowan House is a Protected Structure (RPS Ref. No. 8699). The development will consist of: the demolition of 3 no. existing single storey outbuilding structures (total of 171.5 sq. m) together with part removal of the front existing boundary walls; the change of use of Balnagowan House (Block 1) from office to residential use to provide 4 no. 2 bed residential units (c.354.67 sq.m GFA), together with associated internal and external alterations and refurbishment works to facilitate the conversion (including removal of internal walls/partitions); the construction of a 3 storey duplex & apartment block (Block 2) to provide 4 no. 1 & 3 bed residential units with associated balconies & terraces; & the construction of 22 no. 2 & 3 bedroom 3 storey townhouses with associated private open spaces & balconies, to provide 30 no. residential units (c. 2365.9 sq. m GFA). The overall proposed residential development (c. 3099.81 sq.m GFA) (including Balnagowan House), will comprise 2 no. one bedroom units, 6 no. two bedroom units, & 22 no. three bedroom units. Pedestrian, cyclist, vehicular and emergency access will be provided off The Haven/ St. Mobhi Boithirin via. existing upgraded entrances. The access arrangements include alterations to the existing accesses to front & to the west of Balnagowan House, St. Mobhi Boithirin. The development will also consist of open space provision including all private, communal and public open space, hard and soft landscaping including internal cycle and pedestrian routes, pathways, boundary treatments, as well as a playground of 50sqm within the communal open area, street furniture, car parking (14 no. part internal gnd. fl. garage spaces to the townhouses & 14 no. surface spaces – 2 no. accessible & 5 no. EV charging – with 9 no. of the spaces accessed directly from St. Mobhi Boithirin), bicycle parking (16 no. long & 4 short stay spaces, covered and secure bicycle parking), ESB substations, piped infrastructural services & connections, ducting, plant, waste management & bin store provision, SuDS & attenuation infrastructure, signage, public lighting and all site development incl. all excavation works & service connections. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development.
Permission, 30 homes · Dublin City Council, WEB2324/26
13 Apr 2026Application declared invalid
PROTECTED STRUCTURE : Rectone Developments Ltd intend to apply for PERMISSION for a residential development comprising 30 no. units, on a site of c. 0.476 ha., on lands at Balnagowan House, St. Mobhi Boithirin, Glasnevin, Dublin 9 (the western part of the site fronts The Haven). Balnagowan House is a Protected Structure (RPS Ref. No. 8699). The development will consist of: the demolition of 3 no. existing single storey outbuilding structures (total of 171.5 sq. m) together with part removal of the front existing boundary walls; the change of use of Balnagowan House (Block 1) from office to residential use to provide 4 no. 2 bed residential units (c.354.67 sq.m GFA), together with associated internal and external alterations and refurbishment works to facilitate the conversion (including removal of internal walls/partitions); the construction of a 3 storey duplex & apartment block (Block 2) to provide 4 no. 1 & 3 bed residential units with associated balconies & terraces; & the construction of 22 no. 2 & 3 bedroom 3 storey townhouses with associated private open spaces & balconies, to provide 30 no. residential units (c. 2365.9 sq. m GFA). The overall proposed residential development (c. 3099.81 sq.m GFA) (including Balnagowan House), will comprise 2 no. one bedroom units, 6 no. two bedroom units, & 22 no. three bedroom units. Pedestrian, cyclist, vehicular and emergency access will be provided off The Haven/ St. Mobhi Boithirin via. existing upgraded entrances. The access arrangements include alterations to the existing accesses to front & to the west of Balnagowan House, St. Mobhi Boithirin. The development will also consist of open space provision including all private, communal and public open space, hard and soft landscaping including internal cycle and pedestrian routes, pathways, boundary treatments, as well as a playground of 50sqm within the communal open area, street furniture, car parking (14 no. part internal gnd. fl. garage spaces to the townhouses & 14 no. surface spaces – 2 no. accessible & 5 no. EV charging – with 9 no. of the spaces accessed directly from St. Mobhi Boithirin), bicycle parking (16 no. long & 4 short stay spaces, covered and secure bicycle parking), ESB substations, piped infrastructural services & connections, ducting, plant, waste management & bin store provision, SuDS & attenuation infrastructure, signage, public lighting and all site development incl. all excavation works & service connections. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development.
Permission, 30 homes · Dublin City Council, WEB1836/26
2 Apr 2026Application declared invalid
-PROTECTED STRUCTURE Rectone Developments Ltd intend to apply for PERMISSION for a residential development comprising 30 no. units, on a site of c. 0.476 ha., on lands at Balnagowan House, St. Mobhi Boithirin, Glasnevin, Dublin 9 (the western part of the site fronts The Haven). Balnagowan House is a Protected Structure (RPS Ref. No. 8699). The development will consist of: the demolition of 3 no. existing single storey outbuilding structures (total of 171.5 sq. m) together with part removal of the front existing boundary walls; the change of use of Balnagowan House (Block 1) from office to residential use to provide 4 no. 2 bed residential units (c.354.67 sq.m GFA), together with associated internal and external alterations and refurbishment works to facilitate the conversion (including removal of internal walls/partitions); the construction of a 3 storey duplex & apartment block (Block 2) to provide 4 no. 1 & 3 bed residential units with associated balconies & terraces; & the construction of 22 no. 2 & 3 bedroom 3 storey townhouses with associated private open spaces & balconies, to provide 30 no. residential units (c. 2365.9 sq. m GFA). The overall proposed residential development (c. 3099.81 sq.m GFA) (including Balnagowan House), will comprise 2 no. one bedroom units, 6 no. two bedroom units, & 22 no. three bedroom units. Pedestrian, cyclist, vehicular and emergency access will be provided off The Haven/ St. Mobhi Boithirin via. existing upgraded entrances. The access arrangements include alterations to the existing accesses to front & to the west of Balnagowan House, St. Mobhi Boithirin. The development will also consist of open space provision including all private, communal and public open space, hard and soft landscaping including internal cycle and pedestrian routes, pathways, boundary treatments, as well as a playground of 50sqm within the communal open area, street furniture, car parking (14 no. part internal gnd. fl. garage spaces to the townhouses & 14 no. surface spaces – 2 no. accessible & 5 no. EV charging – with 9 no. of the spaces accessed directly from St. Mobhi Boithirin), bicycle parking (16 no. long & 4 short stay spaces, covered and secure bicycle parking), ESB substations, piped infrastructural services & connections, ducting, plant, waste management & bin store provision, SuDS & attenuation infrastructure, signage, public lighting and all site development incl. all excavation works & service connections. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development.
Permission · Dublin City Council, WEB1774/26
31 Mar 2026Application declared invalid
PROTECTED STRUCTURE: Rectone Developments Ltd intend to apply for PERMISSION for a residential development comprising 30 no. units, on a site of c. 0.476 ha., on lands at Balnagowan House, St. Mobhi Boithirin, Glasnevin, Dublin 9 (the western part of the site fronts The Haven). Balnagowan House is a Protected Structure (RPS Ref. No. 8699). The development will consist of: the demolition of 3 no. existing single storey outbuilding structures (total of 171.5 sq. m) together with part removal of the front existing boundary walls; the change of use of Balnagowan House (Block 1) from office to residential use to provide 4 no. 2 bed residential units (c.354.67 sq.m GFA), together with associated internal and external alterations and refurbishment works to facilitate the conversion (including removal of internal walls/partitions); the construction of a 3 storey duplex & apartment block (Block 2) to provide 4 no. 1 & 3 bed residential units with associated balconies & terraces; & the construction of 20 no. 2 & 3 bedroom 3 storey townhouses with associated private open spaces & balconies, to provide 30 no. residential units (c. 2365.9 sq. m GFA). The overall proposed residential development (c. 3099.81 sq.m GFA) (including Balnagowan House), will comprise 2 no. one bedroom units, 6 no. two bedroom units, & 22 no. three bedroom units. Pedestrian, cyclist, vehicular and emergency access will be provided off The Haven/ St. Mobhi Boithirin via. existing upgraded entrances. The access arrangements include alterations to the existing accesses to front & to the west of Balnagowan House, St. Mobhi Boithirin. The development will also consist of open space provision including all private, communal and public open space, hard and soft landscaping including internal cycle and pedestrian routes, pathways, boundary treatments, as well as a playground of 50sqm within the communal open area, street furniture, car parking (14 no. part internal gnd. fl. garage spaces to the townhouses & 14 no. surface spaces – 2 no. accessible & 5 no. EV charging – with 9 no. of the spaces accessed directly from St. Mobhi Boithirin), bicycle parking (16 no. long & 4 short stay spaces, covered and secure bicycle parking), ESB substations, piped infrastructural services & connections, ducting, plant, waste management & bin store provision, SuDS & attenuation infrastructure, signage, public lighting and all site development incl. all excavation works & service connections. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development.
Permission · Dublin City Council, WEB1738/26
22 Mar 2023Refuse permission
PROTECTED STRUCTURE (RPS Ref. No. 8699) : Permission for a residential development comprising 78 no. units, on a site of c. 0.48 ha, on Lands at Balnagowan House, St. Mobhi Boithirin, Glasnevin, Dublin 9 (the western part of the site fronts The Haven). The development will consist of the demolition of 3 no. existing single storey outbuilding structures (total of 171.5 sq. m) together with part removal of the front existing boundary walls; the construction of 3 no. new apartment blocks (blocks 1-3), with balconies and terraces, to provide 74 no. residential units (c. 6,471 sq. m GFA). The proposed new blocks range between 3 and 5 storeys (including lower ground floor level at block 3) , with a max. height above ground level of 14.85m (to top of lift overrun). (Block 1-3 storeys; block 2 - -4 storeys; and block 3 - part 4/part 5 storeys); and the change of use of Balnagowan House (block 4) from office to residential use to provide 4 no. residential units (c.355 sq. m GFA), together with associated internal and external alterations and refurbishment works to facilitate the conversion(including removal of internal walls/ partitions). The overall proposed residential development (including Balnagowan House), with a total gross floor area of 6,826 sq.m, will consist of 78 no. residential apartment units (including 2 no. duplex units within block 1), comprising 37 no. one bedroom units, 1 no. two bedroom (3 person) unit, 39 no. two bedroom (4 person) units and 1 no. three bedroom unit. Pedestrian, cyclist, vehicular and emergency access will be provided off The Haven/ St. Mobhi Boithirin. The basement car park will be accessed by a new vehicular access point, adjacent to The Haven. The access arrangements include alterations to the existing access to front of Balnagowan House, St. Mobhi Boithirin. The development will also consist of the provision of an ancillary resident's gym, concierge, open space provision including all private, communal and public open space, hard and soft landscaping including internal cycle and pedestrian routes, pathways, boundary treatments and play space, street furniture, basement level (2157 sq. m), car parking (32 no. spaces in total, including car sharing and accessible spaces), motorcycle parking, electric vehicle charging points; bicycle parking (long and short stay spaces including stands and cargo bicycle spaces), ESB substations, piped infrastructural services and connections, ducting, plant waste management provision. SuDS measures (including green roofs); attenuation tanks, signage, public lighting and all site development and excavation works above and below ground. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development. A Natura Impact Statement (NIS)has been prepared in respect of the proposed development. The NIS will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy during office hours at the offices of the relevant planning authority.
Permission, 78 homes · Dublin City Council, 3414/23
Source: National Planning Applications, Department of Housing, Local Government and Heritage, CC BY 4.0. Applicants are not shown.
Designated sites
No designated site (Special Area of Conservation, Special Protection Area, Natural Heritage Area or proposed one) touches this parcel.
Recorded monuments around it
No zone of notification of a recorded monument touches this parcel.
Architectural heritage
No building of the National Inventory of Architectural Heritage stands on this parcel.
Designated sites: National Parks and Wildlife Service. Recorded monuments: Sites and Monuments Record, National Monuments Service. Buildings: National Inventory of Architectural Heritage. Department of Housing, Local Government and Heritage, CC BY 4.0. Works at or in relation to a recorded monument need two months' written notice to the National Monuments Service (National Monuments (Amendment) Act 1994, section 12).
Ground and risks
- Radon
- At the centre of this parcel, about 1 in 20 homes in this area is likely to have high radon levels. Testing a home
- Landslides
- The 1:50,000 map rates the landslide susceptibility here as low.
- Terrain model
- LiDAR of the Office of Public Works, flown in 2011, at 2 m: tile OPW_3205 (ZIP).
- Flooding
- The Office of Public Works publishes its flood maps on floodinfo.ie.
Radon Risk Map of Ireland, Environmental Protection Agency, and Landslide Susceptibility Classification, Geological Survey Ireland, both under CC BY 4.0. LiDAR: contains Irish Public Sector Data (Geological Survey Ireland & the Office of Public Works) licensed under a Creative Commons Attribution 4.0 International (CC BY 4.0) licence.
Download this parcel as DXF, in Irish Transverse Mercator metres, with its neighbours and buildings, for a drawing program. GeoJSON, in WGS 84, suits a map, and KML opens in Google Earth.
Registered freehold land, Tailte Éireann, CC BY 4.0. A parcel is the land of a title, not an address. The owner's name is in the Land Registry of Tailte Éireann: a copy of the folio can be ordered on landdirect.ie, for a fee.